4:30 PM
M6:Preliminary design of LhARA MA RF cavity, FFA magnet, diagnostic system, control & feedback systems complete.
-
4:40 PM
M7: Preliminary design study of LhARA Building concept design, bulk shielding assessment, mechanical systems integration support concepts, vacuum concepts, power consumption & cooling rquirements complete.
-
4:50 PM
M3/9:Validate LhARA plasma simulations with existing Swansea experimental set-up (LhARA M3.1). Progress report of LhARA large diameter plasma experiments and simulations (LhARA M3.2)
-
5:00 PM
M10: Geant4 simulations of beam energy deposition profile (LhARA M4.1)
-
5:10 PM
M11: 18 Month design Review